19. Project Development¶
1. Assignment && week workflow planning¶
1.1 Assignment requirements:¶
Answering questions about final projects.
2. How i did it¶
2.0 What tasks have been completed, and what tasks remain?¶
As described in my FINALPROJECT page, there are differenct part of the work needed to be done and some of them already done from previous assingments or needed minor fixed, while others still remain undeveloped.
I have completed -
-
The ESP32 board as a controller of the smart house from network week
-
The housing of the smart house from computer-controlled machining week
I have not completed -
- Make sensors and actuators running with my ESP32.
RTC, motors/servos,
-
CAD design of the food dispenser
-
Remote control of the food dispenser
2.1 Schedule of my final project¶
-
By June.14 complete the the
-
By June.21 complete the MVP, which the dispenser drops food automatically in a certain time of a day.
-
By June.28 complete the final project, which the dispenser can be controlled remotely